GO-BOND PROJECTS |
|
|
|
|
|
| |
|
|
|
|
|
|
|
Project No. |
PROJECT NAME |
PHASE |
% Cmplt |
COMMENTS |
CONSULTANT |
CONTRACTOR |
|
02.15G |
56th Ave
Roadway and Signalization Improvements |
Construction |
60 |
IN PROGRESS |
ADA Engineering |
Williams Paving |
|
02.15G |
56 Ave Drainage Improvements |
Construction |
95 |
IN PROGRESS |
ADA Engineering |
Williams Paving |
|
02.15G |
56 Ave Lighting and Landscaping |
Construction |
0 |
On Commission Agenda 02/25/08 |
ADA Engineering |
Superior Landscaping |
|
07.06G |
Gateway & Neighborhood Identification |
Design |
50 |
Design due from Administration |
EDSA |
|
|
05.06G |
State Road 7 Intersection Improvements |
Construction |
60 |
IN PROGRESS |
McMahon |
Ranger Construction |
|
04.03G |
Privacy
Wall - NW 44th street |
Construction |
100 |
COMPLETE |
C3TS |
Seldin Construction |
|
05.24G |
44th Street Landscaping |
Construction |
100 |
COMPLETE |
EDSA |
Seldin Construction |
|
06.01G |
Inverrary Blvd. Wall |
Construction |
100 |
COMPLETE |
C3TS |
Seldin Construction |
|
06.02G |
82nd Ave
Wall |
Construction |
100 |
COMPLETE |
C3TS |
Seldin Construction |
|
06.03G |
East
44th Street & Inverrary West Walls |
Construction |
100 |
COMPLETE |
C3TS |
Seldin Construction |
|
G |
Pine Island Wall |
Proposal |
0 |
Awaiting negotiation between City and County |
|
|
|
05.20G |
West Wind Community Center |
Design |
90 |
Design being reworked to meet City's requirements |
Kimley Horn |
|
|
06.21G |
West Wind Park Walkway Lighting |
Design |
100 |
IN PROGRESS |
R. J. Behar |
|
|
06.22G |
Westwind Park Turf Renovation |
Construction |
100 |
COMPLETE |
|
CITY |
|
06.09G |
Veterans Park Decorative Fencing |
Construction |
100 |
COMPLETE |
|
Tropic fence |
|
06.20G |
Veterans Park Baseball Turf |
Construction |
100 |
COMPLETE |
|
Thomas Maintenance |
|
07.32G |
City Hall Park BB Court Resurfacing |
Construction |
100 |
COMPLETE |
|
Accurate Tennis |
|
07.36G |
City Hall Park Tennis Court Resurfacing |
Construction |
100 |
COMPLETE |
|
Accurate Tennis |
|
07.48G |
City Hall Park Turf Replacement |
Construction |
50 |
IN PROGRESS |
|
Thomas Maintenance |
|
07.37G |
City Hall Park Pool |
Design |
0 |
Awaiting scope of project from Admin / CRA |
|
|
|
07.38G |
City Hall Park Community Building |
Design |
0 |
Awaiting scope of project from Admin / CRA |
|
|
|
07.55 |
City Hall Park Addition |
Design |
0 |
Grant being pursued by Grants Writer |
|
|
|
05.19G |
Wolk Park Improvements |
Construction |
100 |
|
|
Tenex |
|
05.22G |
Sadkin Center Renovation |
Design |
50 |
Interior Design in Progress |
Kimley Horn |
|
|
05.26G |
Golf Course Improvements |
Construction |
90 |
IN PROGRESS |
|
|
|
06.05G |
Fire Station 73 Addition & Upgrades |
Design |
0 |
Project being scaled back to fit budget |
|
|
|
06.06G |
Ilene Lieberman Park |
Construction |
60 |
IN PROGRESS |
EDSA |
Coastal |
|
06.13G |
Windermere Comm Center |
Construction |
100 |
COMPLETE |
|
|
|
06.15G |
Jackie Gleason Park Restrooms |
Design |
30 |
Conceptual Drawings accepted by Admin with minor change. |
Kimley Horn |
|
|
06.24G |
Renaissance Park |
Construction |
100 |
COMPLETE |
|
CITY |
|
06.14G |
First City Hall (47 Ave) Restoration |
Design |
0 |
City Engineer to Coordinate with Architect |
|
|
|
G |
Arts and Cultural Center |
Design |
0 |
Admin working on additional funding per instructions from City
Commission |
|
|
|
06.23G |
State Rd 7 Landscaping and Irrigation |
Construction |
100 |
COMPLETE |
|
DOT |
|
07.03G |
State Road 7 County Park Access/Premier Site |
Construction |
70 |
IN PROGRESS |
McMahon |
Weekley |
|
G |
Oakland Park Blvd Paver Replacement |
Construction |
100 |
COMPLETE |
  |